|
Background
In early 2001, the United Arab Emirates (UAE) announced a grant
of up to USD$50 million to the Government of Lebanon (GoL) to
assist mine clearance in the former occupied areas of the south.
The project called “Operation Emirates Solidarity”
(OES) is funded through the generosity of His Highness Sheikh
Zayed bin Sultan Al Nayhan, President of the United Arab Emirates
(UAE).
Late in 2001, the UAE launched a process of tender for the completion
of the work. More than twenty mine action organisations responded
from which ten were short-listed. In March 2002 the UN held a
briefing and orientation over a week for the ten companies, where
they received briefing packs on the specifics of the work along
with IMSMA maps of the OES
project area. Technical advice was provided to the UAE contract
specialists to ensure that the contract documents in terms of
the Statements of Work was accurate and met with the UAE objectives
for clearance. The UN Operations Officer for MACC SL facilitated
the briefings and discussions on behalf of the UAE. Visits to
the mined areas were also conducted so the physical geography
and terrain could be viewed.
Following this week of briefings the companies forwarded their
project details to Abu Dhabi. On request from the UAE mine action
consultants from both within and outside the UN met in Abu Dhabi
to review the proposals. Media coverage of the meeting of experts
ensured transparency and accountability to the process. Two commercial
mine action companies; BACTEC from the UK and MINETECH from Zimbabwe
were selected as contractors. The designated contractual area
was divided geographically into four areas: BACTEC was awarded
OES1
and OES2
and MINETECH OES3
and OES4.
ArmorGroup, a British company was selected to undertake the Quality
Assurance function, and the Landmine Resource Centre within the
faculty of Health Sciences of the University of Balamand, Lebanon
was awarded the Community Liaison contract.
The MACC SL in its tripartite component structure of the UN, the
UAE represented by the UAE Armed Forces and the LAF/ NDO coordinate
the operations of the project.
Completed Phases
Phases 1 and 2
The donation made by the UAE was to fund two phases of work in
the four geographical areas OES1 to OES4. Phase 1 was the clearance
of 288 suspected and known booby-traps located in OES1 which had
been laid by the Israeli forces during the occupation, and Phase
2; the clearance of all landmines and items of unexploded ordnance
from all the four sectors. The completion of these two phases
was estimated to take two years, finishing in May 2004.
Phase 1 of the project was undertaken by BACTEC and commenced
in November 2001. As stated, the objective of this phase was to
clear known and suspected Booby Traps.This phase was completed
on 8 May 2002
Phase 2 of the OES operations involved both companies and the
clearance of landmines and unexploded ordnance from identified
locations within OES1 to OES4. MINETECH commenced its demining
activities on 6 May 2002, and BACTEC on 27 May 2002.
The geographical area for these phases covered a total of 472
square kilometres containing 92 villages in the administrative
districts of Bint Jbeil, Marjayoun, Tyr and one village in Hasbaaya.
The area contained 306 minefields, and was believed to contain
58,161 landmines, predominantly anti-personnel (AP).
Completion of these phases was achieved by 26 August 2003, nine
months ahead of schedule. During the sixteen months it took to
complete the two phases a total of 39,656 mines and items of unexploded
ordnance were located and destroyed. A total of 487 tasks were
completed releasing 4,315,130 square metres of land back to its
owners.
Refer to Phase
2 Statistics for details of clearance by the individual organisations.
This extraordinary achievement has been made possible by the
clear and sustained commitment of the UAE to set and achieve realistic
goals in a predetermined timeframe, the full cooperation and partnership
of the host government, and the tasking coordination, quality
assurance and technical monitoring of the UN and LAF/NDO components
ensuring that all work is completed to the International Mine
Action Standards (IMAS) and the national Technical Standards and
Guidelines (TSG’s).
Phase 3
In early 2003 another mined and former occupied area was identified
and support requested of the UAE by the GoL in anticipation of
the early completion of the first two phases. By May 2002 a third
phase was negotiated and agreed for clearance within the bounds
of the original donation.
This phase was contracted solely to BACTEC and they commenced
operations on 24 June 2003. The geographical area included the
towns of El Qlaiaz, Marjayoun, Blate, Ebel Es Saqi, Rachayya-El-Foukhar,
El Meri and El Khiam all contained within the administrative district
of Marjayoun.
This area covered approximately 87 square kilometres of land
with 75 known minefields, believed to contain 15,254 mines, again
predominantly anti-personnel.
The Quality Assurance function continues to be undertaken by
ArmorGroup on behalf of the UN, and the persons undertaking the
Community Liaison role are now directly sub-contracted by the
UN and financially supported by UNMAS.
Work went extremely well throughout this phase with excellent
integration of the tools from the demining ‘tool box”.
All tasks were completed and final quality assurance checks done
by 24 November. A total of 20,588 mines and items of ordnance
were located and destroyed during this five month period.
For statistics details refer to Phase
3 Statistics
Sweep Through
Commencing 1 December 2003 General and Technical surveys of additional
areas in both the Phase 2 and Phase 3 areas were commenced under
the coordination of the MACC SL Operations Department. These additional
areas were suspected areas advised by the local communities through
the Community Liaison Assistants.
The Quality Assurance staff members headed the Survey Teams supported
by BACTEC Medics and MACC SL Community Liaison Assistants. Following
the survey of these areas which was completed by mid January BACTEC
commenced Technical Surveys, followed by clearance as applicable.
This phase, included as an extension of Phase 3 but dubbed the
“Sweep Through” Phase is being conducted solely by
BACTEC, and financially supported within the bounds of the original
donation of the UAE. It is due to be completed by 31 May 2004.
The complement of BACTEC assets has been joined in April by the
sixth UAE team who comprise a Technical Survey Team, a Manual
Clearance Team and a Mechanical Support Team. The team arrived
at the end of March, successfully completed their training which
was conducted partly before their arrival into Lebanon, and were
accredited for operations on 20 April. They immediately deployed
to assist BACTEC with some of the remaining survey and clearance
tasks of the Phase.
For statistics refer to Sweep
Through Statistics
Future Plans
Discussions have already commenced at the necessary levels on
the planning and defining of a fourth phase for the OES project.
The fourth phase area under proposal is a populated area, large
in geographical size containing potential agricultural land, and
sites of historical and tourism value.
Estimates based on the known threat in the area suggest that clearance
with two commercial contractors could be completed within eighteen
months.
<<TOP>> |